• Event : Network Device and Power shutdown
• Schedule :February 19, 2023 (Sunday) | 10:00 PM – February 20, 2023 (Monday)| 2:13 AM (PHT)
• Activity Details : We have monitored that our network devices were up and stable for three (3) days and 8 hours now since the water leak incident. JAKA site is now fully operational with the help as well of our facilities and admin for cleaning up the affected rooms and floor.
• Service Impact : Network Connectivity and Site power
• Status: Restored
• Event : Network Device and Power shutdown
• Schedule : February 19, 2023 - 10:00 PM (PHT) - Ongoing
• Activity Details : Around 10:00 p.m., we noticed the lobby and server room were filled with water. Tonight, we noticed smoke coming from the server room's extension wires. We decided to turn off network devices for the time being until we could assess the situation further.
• Service Impact : Network Connectivity and Site power
• Status: Ongoing