6th March 2022

Ticket#10125839 | Jaka Building Office | Planned RISE device replacement, scheduled 3 years ago

[3/6/2022 | 11:34 PM] • The Maintenance has been completed successfully, we have tested the affected circuit and has been proven operational. Affected services are confirmed up and running.

[2/21/2022 | 11:34 PM] • Please be advised that one of our Datacenter uplink providers, RISE, will be conducting scheduled maintenance at Jaka Building on March 6, 2022 (2:00-3:00 pm GMT+8). The purpose of this maintenance is to replace their network device located at Jaka Building basement. This activity is estimated to take a maximum of 30 minutes of interruptions within the window time.