• Event : Unscheduled Power Outage – Baguio Site
• Event Start : March 26, 2023 (Sunday) | 6:07 PM – March 27, 2023 (Monday) | 1:34 PM (PHT)
• Status: Our NTB site has been back to normal operations and our network devices has been powered up and stable for two (2) days now. Also, we have been informed that the fire incident is due to an electrical surge/arcing on the building’s battery room as per Bureau of Fire Protection Baguio (BFP) investigation.
• Service Impact : NTB site operations - Back to Normal Operations
• Event : Unscheduled Power Outage – Baguio Site
• Event Start : 6:07PM
• Status: We have confirmed reports of a fire incident at our EMAPTA office in Baguio. We have also confirmed that the fire is out and are currently assessing the situation.
• Service Impact : NTB site operations