• Event : Third-Party Network Provider Maintenance
• Schedule :
Primary Schedule: May 20, 2023 (Saturday) | 12:00AM to 6:00AM (PH Time) - Cancelled Back up Schedule: May 28, 2023 (Sunday) | 12:00AM to 6:00AM (PH Time) - Cancelled
Day 1 Schedule: Primary Schedule: June 10, 2023 (Saturday) | 12:00AM to 6:00AM – New schedule Back up Schedule: June 17, 2023 (Saturday) | 12:00AM to 6:00AM
Day 2 Schedule: Primary Schedule: July 1, 2023 (Saturday) | 12:00AM to 6:00AM – New schedule Back up Schedule: July 8, 2023 (Saturday) | 12:00AM to 6:00AM
• Activity Details :
One of our Data Center will perform a scheduled maintenance on May 20, 2023. This activity aims to create span protection between San Juan - Ermita segments that will establish fiber resiliency and provide with a more stable link and reliable network connection.
• Service Impact : Slightly Increased Latency on one Data Center Link - St. Francis Square Office
• Status: Completed