• Event : Annual Preventive Maintenance
• Schedule : March 27, 2024 (Wednesday) | 11:00 PM to March 30, 2024 (Saturday) | 8:00 AM (PHT)
• Activity Details : Our facilities and building administration will be conducting their annual preventive maintenance. The transformers together with the switch gears and other electrical accessories will be inspected and recalibrated, if necessary, by their third-party contractor.
Here’s the break down of the activity that will incur a total electrical shutdown of the building as the generators set will NOT activity/available. March 27, 2024 – 11:00 PM until March 28, 2024 – 8:00 AM : The affected floors are Basement 3rd to 4th Floor. Elevators 1 and 2 at the lobby near the flower shop will not be operational during this period. March 29, 2024 – 11:00 PM until March 30, 2024 – 8:00 AM : The affected floors are 5th and 7th Floor. Elevators 1 to 4 in the lobby near the overpass will not be operational during this period.
• Service Impact : Building Power Supply