• Event : Facilities and Building Admin Genset Testing
• Schedule : June 27, 2024 (Thursday) | 1:00 PM to 5:00 PM (PHT)—Completed
• Activity Details : Please be advised that this activity has been completed. Normal power was restored at around 01:41 PM
• Service Impact : Building Power Supply—NTB Site
• Event : Facilities and Building Admin Genset Testing
• Schedule : June 27, 2024 (Thursday) | 1:00 PM to 5:00 PM (PHT)
• Activity Details : Our facilities and building admin will be conducting a generator testing today, June 27, 2024 starting at 1PM.
For any unforeseen issue occur during the maintenance activity, power will be shifted automatically to the back up generator that is currently on standby resulting to seconds of downtime.
• Service Impact : Building Power Supply – NTB Site