• Event : Intermittent Internet and Network Connectivity
• Incident Time/Date: March 3, 2025 (Monday) | 11:09 PM (PHT) – March 6, 2025 (Thursday) | 7:11 PM (PHT) - Restored
• Activity Details : Our service provider field engineers have restored the affected circuit after fixing the fiber cut found within our building site premise. PNB site is now operating on full connection redundancy..
• Service Impact : Restored
• Event : Intermittent Internet and Network Connectivity
• Incident Time/Date: March 03, 2025 (Monday) | 11:09 PM (PHT) - Ongoing
• Activity Details : Hi Team,
We would like to inform you that one of our site-to-datacenter circuit is has experienced disruption around 11:09 PM. This has been reported to our provider for further investigation.
Due to the configuration of our network having backup circuits, we expect only partial impact on internet and network connectivity. This may manifest as slow application performance, while remote desktop sessions and VOIP calls may experience intermittent disconnects within a 4-5 minute timeframe while automatic failovers/failback activate.
• Service Impact : Partial Impact on Internet and Network Connectivity – PNB Site