• Event: SM Clark Building Power Maintenance
• Schedule:
Schedule 1: April 29, 2025 (Tuesday) | 06:45 AM – 7:15 AM (PHT) Schedule 2: April 29, 2025 (Tuesday) | 03:30 PM – 4:00 PM (PHT)
• Activity Details:
Please be informed that SM Clark Building Administration has scheduled a power interruption on April 29, 2025 due to the CEDC Line Rerouting Activity, during this period affected areas will be fully supported by Emergency Power.
Power Interruption Schedule:
06:45 AM to 07:15 AM 03:30 PM to 04:00 PM
Transfer Details:
Switch from Normal to Genset Power: 6:45 AM and 3:30 PM Switch from Genset to Normal Power: 7:15 AM and 4:00 PM
For safety reasons, elevator usage will be restricted 5 minutes before each power transfer to minimize the risk of entrapment.
During the power interruption, no impact or downtime is expected on our network devices, as they are supported by Uninterruptible Power Supply (UPS) systems that will maintain continuous power throughout the maintenance activity. However, equipment without battery backup – including desktop computers, lighting, and other devices – may experience temporary power fluctuations.
Should you experience any issues or require assistance during this time, please reach out to:
📌 Facilities and Admin – Available onsite for in-person assistance.
📌 IT Support – Reach out via email at helpme@emapta.com for technical concerns.
• Service Impact: Brief Power Interruption
• Status: Completed