All systems are operational

Past Incidents

24th October 2023

Ticket#10277620 | October 24 to 30, 2023| IPLC | Submarine Repair, scheduled 1 year ago

• Event : IPLC Connectivity Maintenance

• Schedule : October 24, 2023 (Tuesday) | 1:00 AM – October 30, 2023 (Monday) | 1:00 PM (PHT)

• Activity Details : The third-party provider from our service provider will be performing a submarine repair on one of their segment locations between Matara and Yanbu. During the maintenance, a latency increase of 50 milliseconds switch hits plus loss of protection is expected.

• Service Impact : Latency increase and loss of protection in IPLC Connectivity

23rd October 2023

Ticket#10277613 | October 23, 2023| IPLC | Submarine Power Reconfiguration, scheduled 1 year ago

• Event : IPLC Connectivity Maintenance

• Schedule : October 23, 2023 (Monday) | 3:00 PM to 10:00 PM (PHT)

• Activity Details : The third-party provider from our service provider will be performing a submarine optical and power reconfiguration on one of their segment locations. During the maintenance, a latency increase of 50ms switch hits plus loss of protection is expected.

• Service Impact : Latency increase and loss of protection in IPLC Connectivity

• Status: Completed

20th October 2023

Ticket#10277200 | October 20, 2023| IPLC | Network Provider Maintenance, scheduled 1 year ago

• Event :
Service Provider Maintenance | Transfer Cables to Permanent Underground Cable facilities

• Schedule : October 20, 2023 (Friday) 6:00 PM to October 21, 2023 (Saturday) 6:00 AM (PHT)

• Activity Details : Our service provider will have a maintenance on October 20, 2023 to transfer cables from temporary underground to permanent underground in order to reduce any potential risks exposure to our Fiber route and its services.

• Service Impact : Latency increase and loss of protection in IPLC Connectivity

• Status: Completed

19th October 2023

Ticket#10277185 | October 19, 2023| IPLC |Planned | Third-party Network Provider Maintenance, scheduled 1 year ago

• Event : Third Party Essential Maintenance | Hardware Replacement

• Schedule : October 19, 2023 (Thursday) 5:00 AM to 1:30 PM (PHT)

• Activity Details : Our service provider will perform a necessary hardware replacement in London, UK.

During the maintenance activity, an increase latency of 50ms switch plus loss of protection is expected.

• Service Impact : IPLC

• Status: Completed

17th October 2023

Ticket#10275366 | October 17, 2023| IPLC | Planned | IPLC Connectivity Maintenance, scheduled 1 year ago

• Event :
Fiber Pair Troubleshoot

• Schedule : October 17, 2023 (Tuesday) 5:00 PM to 11:00 PM (PHT)

• Activity Details : Our service provider will be going to troubleshoot a fiber pair that producing some “ input signal power low “ alert from their monitoring.

• Service Impact : Latency increase and loss of protection in IPLC Connectivity

• Status: completed

16th October 2023

No incidents reported

15th October 2023

No incidents reported

14th October 2023

RISE Ticket#10277192 | October 14, 2023| Multiple Sites | Network Outage

• Event : Network Outage Affecting Multiple Sites

• Schedule : October 14, 2023 (Saturday) | 11:06 AM – On-going (PHT)

• Activity Details : We have monitored an unplanned network outage affecting multiple sites. We have coordinated this to our service provider for further investigation

• Service Impact : Partial Network and Internet Connectivity Issues

• Status: Restored

Ticket#10275703 | October 12-14, 2023| PNB | PNB Building Power Maintenance, scheduled 1 year ago

• Event : Termination of AMR metering to Main Panel at PNB 5th and 6th Floor

• Schedule : October 12, 2023 (Thursday) 8:00 PM to October 13, 2023 (Friday) 6:00 AM (PHT) – 5th floor PNB

October 13, 2023 (Friday) 8:00 PM to October 14, 2023 (Saturday) 6:00 AM (PHT) – 6th floor PNB

• Activity Details :

Our Building Administrator notified us that EDMI will perform a power maintenance this coming October 12 and 13 at 8:00 PM to 6:00 AM.

A total power shutdown is expected on 5th floor in PNB to give way to termination of meter wires to main panels. Since our infrastructure is dependent on the 5th floor, all floors will be affected due to our main network devices being gracefully powered down. The total power outage duration is expected to last 10 hours.

• Service Impact : PNB 5th and 6th Floor Power Supply

• Status: Completed

13th October 2023

No incidents reported

12th October 2023

RISE Ticket#10276383 | October 12, 2023| IPLC | Network Outage

• Event : Partial Network Outage – RISE DIA(SFS)

• Schedule : October 12, 2023 (Thursday) | 10:55 AM – On-going (PHT)

• Activity Details : We have detected a network outage in your RISE DIA Circuit. This has been escalated to our provider for further investigation. As confirmed, your secondary circuit (IPLC) is still operational; thus, a partial to no impact is expected since the secondary circuit is still operational.

• Service Impact : RISE DIA (Secondary Uplink Circuit)

• Restored by Provider: 11:30AM

RISE Ticket#10276364 | October 12, 2023| Multiple Sites |Unplanned | Network Outage Affecting Multiple Sites

• Event : Network Outage Affecting Multiple Sites

• Schedule : October 12, 2023 (Thursday) | 10:55 AM – On-going (PHT)

• Activity Details : We have monitored an unplanned network outage affecting multiple sites. We have coordinated this to our service provider for further investigation.

• Service Impact : Partial Network and Internet Connectivity Issues

• Status: Restored by Service provider 11:30AM

11th October 2023

RISE Ticket#10275980 | October 11, 2023 | DIA |Partial Network Outage – DIA(SFS)

• Event : Partial Network Outage – DIA

• Schedule : October 11, 2023 (Wednesday) | 6:03 PM -On-going (PH Time)

• Activity Details : We have detected a network outage in your DIA Circuit. This has been escalated to our provider for further investigation.

• Service Impact : DIA (Secondary Uplink Circuit)

• Status: Resolved as of 7:50 PM, RCA to follow with ISP.

RISE Ticket#10274461| October 11, 2023 | Multiple Circuits Down | Unplanned Service Provider Outage

• Event : Multiple Circuits Down | Unplanned Service Provider Outage

• Schedule : October 11, 2023 (Wednesday) 6:03 PM – On-going (PHT)

• Incident Details : Multiple circuits are affected by our service provider's outage.

• Service Impact : Partial outage to multiple sites. Minimal to no impact.

• Status: Resolved as of 7:50 PM, RCA to follow with ISP.

10th October 2023

Power Ticket#10275584 | October 10-11 | PNB | Unplanned Power Interruption

• Event : Unplanned Power Maintenance

• Schedule : October 10-11, 2023 (Tuesday-Wednesday) 11:32 PM -12:07 AM (PHT)

• Incident Details : Unplanned power interruption, affected PNB 4F networking devices.

• Service Impact : No Power on 4F

Ticket#10274461| October 25-26, 2023| IPLC | Internet Service provider Maintenance, scheduled 1 year ago

• Event :
ISP Essential Maintenance

• Schedule :
October 10, 2023 (Tuesday) 8:59 PM – October 11 (Wednesday) 3:00 AM (PHT)

• Activity Details : One of our Internet Service Providers will perform essential maintenance for transmission work on October 10, 2023 to October 11, 2023

• Service Impact : Latency increase on NCP IPLC Connectivity

• Status: Re sched by provider

• Status: Completed

9th October 2023

No incidents reported

8th October 2023

No incidents reported

7th October 2023

No incidents reported