All systems are operational

Past Incidents

31st July 2022

Ticket#10155408 | IBM | Infrastructure Risk Analysis and Mitigation Plan at IBM Building - Quezon City, scheduled 3 years ago

[07/31/2022 | 7:31 PM PHT] • Please be advised that our activity has been completed successfully, All connection and network devices have been tested and confirmed operational.

[07/14/2022 | 5:20 PM PHT] • As part of our continuous effort to provide service reliability, we filed a change request to conduct an Infrastructure Risk Analysis and Mitigation Plan at IBM Building, Quezon City on July 31, 2022 (Sunday) from 1:00 PM to 3:00 PM. The purpose of the activity is to simulate a BCP failover testing on our site. The whole site will be experiencing intermittent LAN and internet connectivity during the maintenance period.

25th July 2022

Ticket#10155225 | IPLC | Planned IPLC Connectivity Maintenance, scheduled 3 years ago

[14/07/2022 | 6:41 AM] • Please be advised that there will be scheduled maintenance on July 25, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 6:00 PM to 4:00 AM (PHT). Our service provider will perform maintenance with vendor for shelf replacement due to “corrupt data inventory”. • During the maintenance window, our service provider has advised us of an expected impact of 50ms switch hits.

15th July 2022

Ticket#10153311 | All Sites | Planned IPLC Connectivity Maintenance, scheduled 3 years ago

[7/6/2022| 6:21 AM] • Please be advised that there will be scheduled maintenance on Friday, June 15, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 4:00 PM to 9:00 PM (PHT), July 15, 2022. During the maintenance window, our service provider has advised us of an expected impact of 50ms switch hits Plus Loss of Protection.

[7/15/2022| 11:00 PM] • Please be advised that the maintenance has been completed successfully, we have tested the affected circuit, and has been proven operational.

14th July 2022

No incidents reported

13th July 2022

No incidents reported

12th July 2022

Power Ticket#10154563 | Neutrinos Building | Unplanned Power Interruption

[12/07/2022 | 6:13 AM] • Please be advised that there is an ongoing power outage at Neutrinos Building that occurred at around 6:03 AM. We're still in coordination with the building admin to know the details of the power outage. Currently, the building supply is running on genset. We will keep you posted on any updates. [12/07/2022 | 10:57 AM] •Please be advised that main power has now been restored at our EMAPTA Baguio office since 10:13 AM today, July 12, 2022. •All network devices are currently operational and reachable. No alerts relating to the power outage has been observed. The power supply for the building has been stable since it was restored but we will continue monitoring throughout the day.

11th July 2022

No incidents reported

10th July 2022

No incidents reported

9th July 2022

Ticket#10153901 | IPLC | IPLC Connectivity Maintenance (July 9, 2022), scheduled 3 years ago

[07/09/2022 | 11:00 PM] Please be advised that the maintenance has been completed successfully, we have checked the affected circuit and has been proven operational. IPLC and VPC latency are within the normal range.

[07/08/2022 | 7:57 AM] •Please be advised that there will be scheduled maintenance on July 9, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 6:00 AM to 11:00 PM (PHT). Our service provider will perform fiber works to rectify span loss that was detected proactively.

Ticket#10153511 | IPLC | IPLC Connectivity Maintenance - (July 9, 2022), scheduled 3 years ago

[07/06/2022 | 7:07 PM] • Please be advised that there will be scheduled maintenance on Saturday, July 09, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 6:00 AM to 11:00 PM (PHT). Our service provider will conduct emergency fiber works to rectify span loss on Philippine Backhaul detected proactively. During the maintenance window, our service provider has advised us of an expected impact of 50ms switch hits Plus Loss of Protection.

Ticket#10153809 | IPLC |IPLC Connectivity Maintenance (July 8, 2022), scheduled 3 years ago

[07/07/2022 | 9:23 PM PHT] • Please be advised that there will be scheduled maintenance on July 8, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 5:00 AM to 12:00 PM (PHT). Our service provider will perform emergency fiber replacement. During the maintenance window, our service provider advised us of the expected impact of 50ms switch hits within the change window.

8th July 2022

Ticket#10153867 | Baguio | Unplanned Data Center Uplink going to Emapta Pilando Center is down

[7/8/2022 | 4:08 AM] • Please be advised that one of the Data Center uplinks going to our office in Pilando Center, Baguio was monitored down around 4:08 AM. And it was monitored up around 4:18 AM and has been stable for 15 minutes. We will continue to monitor for stability. We also raise the issue to our Internet Service Provider to check the root cause of this downtime.

Ticket#10153234 | Philippines to AU IPLC | Planned | IPLC Connectivity Maintenance (July 8, 2022), scheduled 3 years ago

[7/5/2022| 9:08 PM] • Please be advised that the maintenance has been completed successfully, we have checked the affected circuit and has been proven operational. IPLC and VPC latency are within the normal range. Should you have any questions, please let us know.

[7/5/2022| 9:08 PM] • Please be advised that there will be scheduled maintenance on July 8, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 8:00 AM to 2:00 PM (PHT). Due to the way the network is set up, users will automatically failover to the VPN when the IPLC becomes unavailable.

Ticket#10153809 | IPLC| IPLC Connectivity Maintenance (July 8, 2022), scheduled 3 years ago

[07/05/2022 | 9:08 PM PHT] • Please be advised that the maintenance has been completed successfully, we have checked the affected circuit and has been proven operational. IPLC and VPC latency are within the normal range. Should you have any questions, please let us know

[07/05/2022 | 9:08 PM PHT] • Please be advised that there will be scheduled maintenance on July 8, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 8:00 AM to 2:00 PM (PHT). Our service provider will perform a hardware restart to avoid unplanned and longer outages anytime and advise us of the expected impact of 2 hours of an outage within the change window. Due to the way the network is set up, users will automatically failover to the VPN when the IPLC becomes unavailable.

7th July 2022

Power Ticket#10153572 | Neutrinos Building | Unplanned Power Interruption

[7/7/2022 | 12:11 AM] • Please be advised that the main power supply at Neutrinos Building is now back on the main power. No outstanding issues have been observed related to the maintenance.

[7/7/2022 | 12:12 AM] • Please be advised that there is an ongoing power outage at Neutrinos Building that occurred 11:14 PM. We're still in coordination with the building admin to know the details of the power outage. Currently, the building supply is running on genset. We will keep you posted on any updates.

6th July 2022

Ticket#10153229 | IPLC | IPLC Connectivity Maintenance (July 6, 2022), scheduled 3 years ago

[07/05/2022 | 5:37 PM PHT] • Please be advised that the maintenance has been completed successfully, we have checked the affected circuit, and has been proven operational. IPLC and VPC latency are within the normal range.

[07/05/2022 | 8:51 PM PHT] • Please be advised that there will be scheduled maintenance on July 6, 2022, to be conducted by one of our Internet Service Providers. The maintenance window will be from 5:00 AM to 12:00 PM (PHT). Our service provider will perform emergency fiber replacement. During the maintenance window, our service provider advised us of the expected impact of 50ms switch hits within the change window.