#SR-257442 | July 19, 2025 | Orient Square Building, Ortigas | Site to Datacenter Circuit Network Maintenance

• Event: Installation of Additional Uninterruptible Power Supply

• Schedule: July 19, 2025 (Saturday) | 01:00 PM – 03:00 PM (PHT)

• Activity Details:

Hi Team,

As part of on-going efforts to improve service reliability and network availability, one of our service providers will conduct maintenance to install an additional uninterruptible power supply on their network equipment.

During the maintenance window, a maximum of 2 hours interruption on one of our OSB Site to Datacenter Circuit is expected. However, due to the configuration of our network having backup circuits, we expect only a partial impact on internet and network connectivity as we have automatic failovers in place.

During the failover process, you may experience brief disruptions on any of the following below:

  • Choppy or Dropped VoIP Calls – Poor audio quality, delays, or dropped calls on platforms like Zoom, Teams, or Skype.
  • Delayed Emails & Messages – Slower delivery of emails (Outlook, Gmail) and messages in chat apps like Slack and Teams.
  • Latency Issues – Delays in response times, particularly for real-time applications.
  • Remote Desktop (RDP) Disruptions – Lag, session timeouts, or disconnections when accessing remote systems.

• Service Impact: Partial Impact on Internet and Network Connectivity

Past Incidents

20th November 2022

Ticket#10180739 | November 20, 2022 | NTB, PNB, BET and IBM | Internet Service Provider Router Software Upgrade, scheduled 2 years ago

• Event: Internet Service Provider Router Software Upgrade

• Schedule: November 20, 2022 (Sunday) | 5:00 AM to 10:00 AM (PHT)

• Activity Details: Our internet service provider has been upgraded the software of their networking device successfully. We have tested the affected circuit and has been proven operational.

• Result: Completed.

• Event: Internet Service Provider Router Software Upgrade

• Schedule: November 20, 2022 (Sunday) | 5:00 AM to 10:00 AM (PHT)

• Activity Details: One of our internet service providers will be updating the networking device software to the most recent version.

• Service Impact: During this window time a 1-hour downtime on their circuits is expected. But due to the way our network is setup, there should be partial to NO impact during their maintenance.

17th November 2022

Ticket#10181232 | November 17, 2022| NTB and SFS | IPLC Connectivity Maintenance, scheduled 2 years ago

• Event : IPLC Connectivity Maintenance

• Schedule: November 17, 2022 (Thursday) | 5:00 AM to 1:00 PM (PHT)

• Activity Details: Our third-party service provider will be carrying out a preventive maintenance on their fiber network.

• Service Impact: During the maintenance window, there would be an expected impact of 50ms switch hits plus loss of protection.

• Maintenance Result: Successfully Completed

13th November 2022

Ticket#10180658 | November 13, 2022 | SFS | BCP Network Failover Testing, scheduled 2 years ago

• Event: BCP Failover Testing Activity

• Schedule: November 13, 2022 - November 14, 2022 - 10:00 PM - 12:00 AM (PHT)

• Impact: Intermittent LAN and Internet connectivity

• Activity Result: Successfully Completed

Ticket#10180654 | November 13, 2022 | TIP | BCP Network Failover Testing, scheduled 2 years ago

• Event: BCP Failover Testing Activity

• Schedule: November 13, 2022 - 3:00 PM - 5:00 PM (PHT)

• Impact: Intermittent LAN and Internet connectivity

• Activity Maintenance Result: Successfully Completed

Ticket#10181431 | November 13, 2022 | TIM Data Center | Monthly load testing of Generator Sets, scheduled 2 years ago

• Event: TIM Data Center Monthly load testing of Generator Sets

• Schedule: November 13, 2022 (Sunday) | 8:40 AM to 5:25 PM (PHT)

• Service Impact: Non-Service Affecting

• Activity Result: Canceled

12th November 2022

Power Ticket# | November 12, 2022 | JMT | Planned Power Interruption

• Event: Power Interruption

• Schedule: November 12, 2022 (Sunday) | 8:00 AM to 5:00 PM (PHT)

• Activity Details: During power maintenance, the JMT power source must be switched.

• Service Impact: JMT's Main source of Power

• UPDATE 1: The Maintenance has been completed successfully, we have checked the functionality of all site devices, and has tested operational.

11th November 2022

No incidents reported

10th November 2022

Ticket#10181163 | November 10 - 11, 2022| JKB | Rectification of software due to end of life support, scheduled 2 years ago

• Event: Third-party provider Software Upgrade

• Schedule: November 10, 2022 (Thursday) – November 11, 2022 (Friday) | 10:00 PM to 6:00 AM (PHT)

• Service Impact: Maximum of 60 minutes downtime on the affected circuit during maintenance window time. Because another uplink to our internet gateway is available, the impact will be minimal to none.

• Maintenance Activity Result: Successfully Completed

9th November 2022

No incidents reported

8th November 2022

Ticket#10180268 | November 8 - 9, 2022 | IBM | Emergency Network Maintenance, scheduled 2 years ago

[09/11/2022 | 7:13 AM] • Our Internet Service Provider confirmed that the activity had been completed successfully.

[07/11/2022 | 11:30AM] • Third-party circuit provider at IBM office will be performing emergency network maintenance due to software end-of-life. A maximum of 60 minutes downtime is expected during the window between November 8 - 9, 10:00PM to 6:00AM (PHT). Partial to no impact is expected due to having another internet uplink present at the site.

7th November 2022

Network and Internet Ticket#10180463 | November 7, 2022 | The Ignacia Place (TIP) | Partial Network Outage

[09/11/2022 | 4:38 PM] • Our internet service provider already completed the restoration of the circuit uplink. We have monitored that the uplink connection is stable. We will request for a RCA from our service provider and will provide it upon your request.

[07/11/2022 | 9:18 PM] • Please be advised that we have monitored one of our circuit uplinks to the Data Center at The Ignacia Place as down. We have raised this to our internet service provider for further investigation.

• Further updates will be provided as soon as they are available.

6th November 2022

No incidents reported

5th November 2022

Ticket#10179859 | November 5, 2022 | PNB, SFS and TIP | Access Point Firmware Upgrade, scheduled 2 years ago

[05/11/2022 | 10:56 AM] • Please be advised that the Access Point firmware upgrade was completed successfully. During the activity, no problems or alerts were encountered.

[04/11/2022 | 9:51 AM] • Please be advised that on November 5, 2022, we will be performing a firmware upgrade on the wireless devices across the mentioned sites from 10:00 AM to 1:00 PM (PHT). This upgrade is being performed to address the current vulnerability on our access points. During the maintenance, there may be intermittent wireless connectivity.

4th November 2022

No incidents reported