14th December 2024

Ticket#126315 | December 14 - 15 , 2024| Philippine National Bank (PNB-Makati) | Energization of Ring Main Unit Switchgear (RMU) and Service Transformer, scheduled 6 months ago

• Event : Planned Power Service Maintenance at Philippine National Bank (PNB-Makati)

• Schedule : December 14, 2024 (Saturday) | 5:30 AM to December 15, 2024 (Sunday) | 7:00 AM - PHT

• Activity Details : Our facilities and building administration will be performing an energization of ring main unit (RMU) switchgear and one (1) unit service transformer as part of their on-going transformer and RMU switchgear installation project. Through this project, we can prevent and stop interruption of business during normal operation, protect huge business loss, and protect our electrical system from overload, short-circuit current fault and ground-fault current.

During the maintenance activity, a 1 to 3 seconds of power fluctuation during the transition from normal to genset power and vice versa is expected.

Prior to start of the activity. The Property Management Office (PMO) will visit all tenants per floor. Feel free to reach out our @SD Facilities and Admin if you have any questions or concern.

• Service Impact : 1 to 3 Seconds of Power Fluctuation From Normal Power to Genset and Vice Versa

10th December 2024

No incidents reported

9th December 2024

No incidents reported

8th December 2024

No incidents reported

7th December 2024

Ticket#127742 | December 07, 2024|SM Clark Tech Hub (SCT) | Monthly Load Testing for Generators, scheduled 6 months ago

• Event : Planned Power Service Maintenance at SM Clark Tech Hub (SCT) - December 07, 2024

• Schedule : December 07, 2024 (Saturday) | 2:00 PM to 3:00 PM (PHT)

• Activity Details : This maintenance activity has been completed as scheduled.

• Service Impact : Non-service impacting - Completed


• Event : Planned Power Service Maintenance at SM Clark Tech Hub (SCT) - December 07, 2024

• Schedule : December 07, 2024 (Saturday) | 2:00 PM to 3:00 PM (PHT)

• Activity Details : Our facilities and building administration will be conducting their monthly load testing for our generators to ensures the reliability and readiness of our equipment to any power interruptions that will be encountered. See below activity details.

Elevator access will be restricted during the following times: From 1:55 PM to 2:00 PM (switching to emergency power) From 2:55 PM to 3:00 PM (switching back to normal power)

This is a non-service impacting activity.

• Service Impact : Non-service impacting

6th December 2024

No incidents reported

5th December 2024

No incidents reported

4th December 2024

RISE Ticket#INC-127645 | December 4, 2024| Multiple Sites |Internet Upstream Issues

Hi Team,

We are aware of some network and internet connectivity issues being experienced across Philippines' Emapta sites. Preliminary investigation showed that there is a possible upstream issue on an international circuit that our provider is peered with. We have raised this concern to our provider for their further checking, as well as a temporary solution to avoid the problematic circuit.

We will keep you posted with any further updates.