7th December 2024

Ticket#113350 | December 07 to 09, 2024|The Orient Square Building (OSB-Ortigas) |Replacement of Transformers, scheduled 6 months ago

• Event : Planned Power Service Maintenance at The Orient Square Building (OSB-Ortigas)

• Schedule : December 07, 2024 (Saturday) | 2:00 AM to December 09, 2024 (Monday) | 12:00 Midnight (PHT)

• Activity Details : We received a memo from our facilities and building administration to perform a replacement of transformers 1 and 3.

See below activity details for our common reference:

During the above dates, power to the building will be supplied exclusively by a generator, as the transformers will be offline. Please expect brief power interruptions during the switchover to and from the generator, which will take only a matter of seconds. We advise all accounts to save any ongoing work and unplug sensitive electronic devices during these times to prevent data loss or equipment damage.

Emergency Lighting: Emergency lighting will remain operational during the switchovers to ensure safety and visibility within the building.

Alternative Arrangements: We encourage you to plan your activities around the scheduled dates to minimize inconvenience. If you have critical operations that may be affected, please inform us as soon as possible so we can discuss potential solutions.

If you have questions or clarifications just send an email to our facilities and building admin team @sd.facilityandadmin@emapta.com.

• Service Impact : Brief Series of Power Service Interruptions - OSB

23rd November 2024

Ticket#117288 | November 23, 2024| All Sites | Software/Operating System Upgrade, scheduled 6 months ago

• Event : Planned - Site to Datacenter Network Maintenance at All Sites

• Schedule : November 23, 2024 (Saturday) | 1:00 AM to 5:00 AM (PHT)

• Activity Details : One of our service providers will be conducting a software / operating system upgrade on one of their network monitoring systems to ensure updates in the system is being check and logs accurately.

This is a non-service impacting maintenance activity.

• Service Impact : Non-service impacting – All Sites

Ticket#117240 | November 23, 2024| SCT (Pampanga) and JEG (Cebu)| Link Migration, scheduled 6 months ago

• Event : Planned - Site to Datacenter Network Maintenance at SCT (Pampanga) and JEG (Cebu

• Schedule : November 23, 2024 (Saturday) | 1:00 AM to 5:00 AM (PHT)

• Activity Details : As part of the continued efforts to increase service availability and internet quality, one of our service providers will be conducting a link migration on one of the backhaul links in manila to another switch.

This is a non-service impacting activity maintenance but possible changes in latency may observed as traffic is switchover through alternative links.

• Service Impact : Non-service impacting – SCT and JEG Site

14th November 2024

Ticket#113347 | November 14 to 18, 2024| The Orient Square Building (OSB-Ortigas) | Replacement of Transformers, scheduled 7 months ago

• Event : Planned Power Service Maintenance at The Orient Square Building (OSB-Ortigas)

• Schedule : November 14, 2024 (Thursday) | 8:00 PM to November 18, 2024 (Monday) | 6:00 AM (PHT)

• Activity Details : We received a memo from our facilities and building administration to perform a replacement of transformers 1 and 3.

See below activity details for our common reference:

During the above dates, power to the building will be supplied exclusively by a generator, as the transformers will be offline. Please expect brief power interruptions during the switchover to and from the generator, which will take only a matter of seconds. We advise all accounts to save any ongoing work and unplug sensitive electronic devices during these times to prevent data loss or equipment damage.

Emergency Lighting: Emergency lighting will remain operational during the switchovers to ensure safety and visibility within the building.

Alternative Arrangements: We encourage you to plan your activities around the scheduled dates to minimize inconvenience. If you have critical operations that may be affected, please inform us as soon as possible so we can discuss potential solutions.

If you have questions or clarifications just send an email to our facilities and building admin team @sd.facilityandadmin@emapta.com.

• Service Impact :Brief Series of Power Service Interruptions - OSB

13th November 2024

No incidents reported

12th November 2024

No incidents reported

11th November 2024

No incidents reported

10th November 2024

Ticket#INC-115115 | November 10, 2024 | BET, IBM, NTB, ASB, SCT, JMT, and PNB | Multiple Sites Network and Internet Connectivity Interruptions - Recovered

• Event : Unplanned | Multiple Site to Datacenter Connectivity Interruptions - November 10, 2024

• Incident : November 10, 2024 (Sunday) | 6:42 PM to 6:53 PM (PHT) – First Instance November 10, 2024 (Sunday) | 8:04 PM to 8:26 PM (PHT) – Second Instance, Ongoing Restoration

• Activity Details : Please be advised that the affected circuits have been recovered. According to our service provider, backhaul links have been repaired. The impacted circuits in our infrastructures have been recovered and monitored stable for 5 hours

All circuits are now fully operational with redundancy.

• Service Impact : Recovered


• Event : Unplanned | Multiple Site to Datacenter Connectivity Interruptions - November 10, 2024

• Incident : November 10, 2024 (Sunday) | 6:42 PM to 6:53 PM (PHT) – First Instance November 10, 2024 (Sunday) | 8:04 PM to 8:26 PM (PHT) – Second Instance, Ongoing Restoration

• Activity Details : We have observed second instance of interruption at around 8:04 PM and as per our service provider this is due to multiple backhaul links are down, and their restoration team is currently en route to the fault location to conduct necessary checks. No ETR yet provided to us but will do necessary follow ups.

During the interruptions, only partial impact on network and internet connectivity is expected as we have another site to datacenter connectivity available for connection redundancy

We do apologize for any inconvenience it has caused.

• Service Impact : Partial Network and Internet Connectivity Interruptions on both wired and wireless connection – BET, IBM, NTB, ASB, SCT, JMT, and PNB

9th November 2024

Ticket#113368 | November 09, 2024| The Orient Square Building (OSB-Ortigas) |Generator Set#3 Power Load Testing - Completed, scheduled 7 months ago

• Event : Planned Power Service Maintenance at The Orient Square Building (OSB-Ortigas)

• Schedule : November 09, 2024 (Saturday) | 9:00 AM 11:00 AM (PHT)

• Activity Details : This maintenance activity has been successfully completed as scheduled.

• Service Impact : Completed


• Event : Planned Power Service Maintenance at The Orient Square Building (OSB-Ortigas)

• Schedule : November 09, 2024 (Saturday) | 9:00 AM 11:00 AM (PHT)

• Activity Details : We received a memo from our facilities and building administration that they will be conducting a power run test on the generator set in preparation of the upcoming first mobilization phase of the replacement of transformers on November 14, 2024.

Please expect power fluctuations lasting 5-10 seconds during the transfer between normal power and Genset power, and vice versa.

If you have questions or clarifications, just send an email to our facilities and building admin team @sd.facilityandadmin@emapta.com.

• Service Impact : 5 to 10 seconds of Power Fluctuation Between Switchover of Normal to Genset (Vice Versa) - OSB

8th November 2024

No incidents reported

7th November 2024

No incidents reported

6th November 2024

Ticket#112866 | November 06, 2024| SM Clark Tech Hub (SCT)| Core Router Maintenance Activity, scheduled 7 months ago

• Event : EMERGENCY | Planned - Internet Service Provider Network Maintenance at SM Clark Tech Hub (SCT)

• Schedule : November 06, 2024 (Wednesday) | 4:00 AM to 6:00 AM (PHT)

• Activity Details : Following the yesterday’s emergency maintenance of one of our service providers, they have requested to have additional activity that includes service migration on one of their core routers.

During the maintenance activity, only partial impact on network and internet connectivity is expected as we have another site to datacenter connectivity available for connection redundancy.

• Service Impact : Partial impact on network and internet connectivity - SCT

• Status: Completed

Ticket#112874 | November 06, 2024| The Ignacia Place (TIP) | Core Router Maintenance Activity, scheduled 7 months ago

• Event : EMERGENCY | Planned - Internet Service Provider Network Maintenance at The Ignacia Place (TIP)

• Schedule : November 06, 2024 (Wednesday) | 4:00 AM to 6:00 AM (PHT)

• Activity Details : One of our service providers will be conducting an emergency maintenance on of their core routers that includes service migration.

During the maintenance activity, only partial impact on network and internet connectivity is expected as we have another site to datacenter connectivity available for connection redundancy.

• Service Impact : Partial impact on network and internet connectivity - TIP

5th November 2024

Ticket#111910 | November 05, 2024| SM Clark Tech Hub (SCT)| Core Router Maintenance Activity, scheduled 7 months ago

• Event : EMERGENCY | Planned - Internet Service Provider Network Maintenance at SM Clark Tech Hub (SCT)

• Schedule : November 05, 2024 (Tuesday) | 4:00 AM to 5:00 AM (PHT)

• Activity Details : One of our service providers will be conducting an emergency maintenance to one of their core routers to implement a potential permanent solution that will help prevent future occurrences and confirm the root cause of the recent incident on the circuit and to enhance their service reliability.

During the maintenance activity, only partial impact on network and internet connectivity is expected as we have another site to datacenter connectivity available for connection redundancy.

• Service Impact : Partial impact on network and internet connectivity - SCT

• Status: Completed

4th November 2024

No incidents reported

19th October 2024

Ticket#SR-91926 | November 10, 2024 | JEG Site | Third Party Service Provider Maintenance Activity, scheduled 7 months ago

• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : November 10, 2024 (Sunday) | 1:00AM – 5:00AM PHT – New Schedule

• Activity Details : This is to inform you that this network maintenance activity by one of our Site-to-Data Center providers at JEG site at Cebu has been rescheduled to 1:00AM – 5:00AM of Sunday, November 10, 2024 . The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting


• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : October 27, 2024 (Sunday) | 1:00AM – 5:00AM PHT – New Schedule

• Activity Details : Dear Team,

This is to inform you that this network maintenance activity by one of our Site-to-Data Center providers at JEG site in Cebu has been rescheduled to 1:00AM – 5:00AM of Sunday, October 27, 2024 . The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting


• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : October 19, 2024 (Saturday) | 1:00AM – 3:00AM PHT

• Activity Details : Dear Team,

This is to inform you that there will be a network maintenance activity by one of our Site-to-Data Center providers.

The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting

• Status: Completed

Ticket#SR-91920 | November 10, 2024 | SCT Site | Third Party Service Provider Maintenance Activity, scheduled 7 months ago

• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : November 10, 2024 (Sunday) | 1:00AM – 5:00AM PHT – New Schedule

• Activity Details : This is to inform you that this network maintenance activity by one of our Site-to-Data Center providers at SCT site at Clark Pampanga has been rescheduled to 1:00AM – 5:00AM of Sunday, November 10, 2024 . The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting


• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : October 27, 2024 (Sunday) | 1:00AM – 5:00AM PHT – New Schedule

• Activity Details : This is to inform you that this network maintenance activity by one of our Site-to-Data Center providers at SCT site at Clark Pampanga has been rescheduled to 1:00AM – 5:00AM of Sunday, October 27, 2024 . The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting


• Event : Planned Maintenance Activity | Backhaul link migration by service provider

• Schedule : October 19, 2024 (Saturday) | 1:00AM – 3:00AM PHT

• Activity Details : Dear Team,

This is to inform you that there will be a network maintenance activity by one of our Site-to-Data Center providers.

The activity will focus on migrating one of their backhaul links for increase service availability.

No service impact expected for this activity.

• Service Impact : Non-service impacting

• Status: completed