All systems are operational
Scheduled Maintenance
#SR-231466| June 12, 2025 | IPLC Connectivity Maintenance

• Event: Subsea Fiber Cable Maintenance

• Schedule: June 12, 2025 (Thursday) | 02:00 AM – 03:00 AM (PHT)

• Activity Details:

Please be advised that our service provider will perform fiber span loss rectification maintenance on Thursday, June 12, 2025, from 2:00 AM to 3:00 AM (PHT).

During the maintenance window, a 15-minute service interruption on the IPLC is expected. However, due to the way our network is setup, traffic should be automatically failover to the VPN connection that will result to a latency increase on VPC/RDP’s.

• Service Impact: Service interruption in IPLC Connectivity

#SR-231564 | June 16, 2025 | TIP, ASB | Site to Datacenter Circuit Network Maintenance

• Event: Network Device Software Upgrade

• Schedule: June 16, 2025 (Monday) | 12:00 AM – 06:00 AM (PHT)

• Activity Details:

Hi Team,

We would like to inform you that one of our service providers will be performing a software upgrade of their network device to the latest version to enhance network security, performance, and overall system functionality.

During the maintenance window, a maximum of a 2-hour interruption on one of our sites to datacenter circuit is expected. However, due to the configuration of our network having backup circuits, we expect only a partial impact on internet and network connectivity as we have automatic failovers in place.

During the failover process, you may experience brief disruptions on any of the following below:

Choppy or Dropped VoIP Calls – Poor audio quality, delays, or dropped calls on platforms like Zoom, Teams, or Skype. Delayed Emails & Messages – Slower delivery of emails (Outlook, Gmail) and messages in chat apps like Slack and Teams. Latency Issues – Delays in response times, particularly for real-time applications. Remote Desktop (RDP) Disruptions – Lag, session timeouts, or disconnections when accessing remote systems.

• Service Impact: Partial Impact on Internet and Network Connectivity

Past Incidents

2nd March 2025

Ticket#169831 | March 02, 2025| IBM Site| IT Infrastructure Maintenance, scheduled 3 months ago

• Event : Planned Infrastructure Risk Analysis and Mitigation Plan at IBM Site (Eastwood)

• Schedule : March 02, 2025 (Sunday) | 1:00 PM to 3:00 PM (PHT)

• Activity Details : As part of our endeavor to enhance our service reliability and availability we will be conducting our Annual Business Continuity Plan for Network Failover Testing.

During the maintenance activity there will be a series of network and internet interruptions on both LAN/wired and wireless.

Steps have been taken to ensure that minimal to no users are affected during this activity.

Another advisory will be sent once this maintenance has been completed.

• Service Impact : Network and Internet Connectivity Interruptions on Both Wired and Wireless Connection – IBM Site

• Status: Canceled

1st March 2025

No incidents reported

28th February 2025

No incidents reported

27th February 2025

Network and Internet Ticket#INC-172521 | February 27, 2025 | SMT and SCT | Unplanned | Loss of Internet Connectivity at SM Sky City Clark Pampanga (SCT) and SM Mega Tower Ortigas (SMT)

• Event : Site-to-Datacenter Network Interruptions

• Incident Time/Date : February 27, 2025 (Thursday) | 10:12 PM to 11:43 PM (PHT) | SMT – Restored, monitoring stability February 27, 2025 (Thursday) | 10:12 PM to 10:37 PM (PHT) | SCT – Restored, monitoring stability

• Activity Details : Dear Team,

Both SCT and SMT sites internet and network connectivity are monitored up.

We are closely monitoring the stability of the affected uplinks.

If you are still experiencing issues, please don’t hesitate to report them to helpme@emapta.com

• Service Impact : Loss of Internet Connectivity at SM Sky City Clark Pampanga (SCT) and SM Mega Tower Ortigas (SMT)


• Event : Site-to-Datacenter Network Interruptions

• Incident Time/Date : February 27, 2025 (Thursday) | 10:12 PM (PHT)– Ongoing (SMT Site) February 27, 2025 (Thursday) | 10:12 PM to 10:37 PM (PHT)– Recovered and for stability monitoring (SCT Site)

• Activity Details :Dear Team,

SM Megatower redundant circuits have been impacted at the same time, even though we are still coordinating with both vendors, it is apparent that the issue lies in the circuit last mile within the facility that has caused two totally independent circuits to go down simultaneously in which Emapta has no control over.

We are closely working with our vendors to gather more information about the outage

• Service Impact : Loss of Internet Connectivity at SM Sky City Clark Pampanga (SCT) and SM Mega Tower Ortigas (SMT)


• Event : Site-to-Datacenter Network Interruptions

• Incident Time/Date : February 27, 2025 (Thursday) | 10:12 PM (PHT)– Ongoing (SMT Site) February 27, 2025 (Thursday) | 10:12 PM to 10:37 PM (PHT)– Recovered (SCT Site)

• Activity Details :Dear Team,

With regards to both of the SMT redundant circuits, our service provider is already coordinating with their third-party for their further investigation.

We apologies for the inconvenience it has caused.

• Service Impact : Loss of Internet Connectivity at SM Sky City Clark Pampanga (SCT) and SM Mega Tower Ortigas (SMT)


• Event : Site-to-Datacenter Network Interruptions

• Incident Time/Date : February 27, 2025 (Thursday) | 10:12 PM (PHT)– Ongoing (SMT Site) February 27, 2025 (Thursday) | 10:12 PM to 10:37 PM (PHT)– Recovered (SCT Site)

• Activity Details : Dear Team,

We have monitored that SCT site internet connectivity has been recovered.

We apologies for the inconvenience it has caused.

• Service Impact : Loss of Internet connectivity at SCT and SMT Site


• Event : Site-to-Datacenter Network Interruptions

• Incident Time/Date : February 27, 2025 (Thursday) | 10:12 PM (PHT)– Ongoing (SMT Site) February 27, 2025 (Thursday) | 10:19 PM (PHT)– Ongoing (SCT Site)

• Activity Details : Dear Team,

We have observed that both of our site-to-datacenter circuits at SMT and SCT site were monitored down and already reported to our service provider for their investigation.

During the incident, internet is intermittently unreachable.

• Service Impact : Loss of Internet connectivity at SCT and SMT Site

26th February 2025

No incidents reported

25th February 2025

Network and Internet #INC-170780 | February 25, 2025| TIP | Unplanned | Site to Datacenter Circuit Network Interruption

• Event : Partial Interruption on Network and Internet Connectivity

• Schedule : February 25, 2025 (Tuesday) | 1:54 PM - Ongoing (PHT)

• Activity Details :

Please be informed that one of our Site to Datacenter Circuit is currently experiencing an outage and we are currently coordinating with our circuit provider to know more about the situation.

Due to the configuration of our network having backup circuits, we expect only partial impact on internet and network connectivity. This may manifest as slow application performance, while remote desktop sessions and VOIP calls may experience intermittent disconnects within a 4-5 minute timeframe while automatic failovers/failback activate.

• Service Impact : Partial Interruption on Network and Internet Connectivity

24th February 2025

Ticket#169983 | February 24, 2025| NTB (Baguio) |Partial Interruption on Network and Internet Connectivity

• Event : Unplanned – Site to Datacenter Circuit Network Interruption

• Schedule : February 24, 2025 (Monday) | 6:07 PM (PHT) - 6:35 PM - Restored

• Activity Details : We have observed that the affected site to datacenter circuit is now UP and restored. NTB Site is now on full connection redundancy.

• Service Impact : Restored


• Event : Unplanned – Site to Datacenter Circuit Network Interruption

• Schedule : February 24, 2025 (Monday) | 6:07 PM (PHT) - Ongoing

• Activity Details : We have observed that one of our site to datacenter circuit at NTB is currently down and already coordinated with our service provider for their checking and investigation.

During the incident, only partial impact on network and internet connectivity is expected as we have another site to datacenter connection available for redundancy.

• Service Impact : Partial impact on network and internet connectivity – NTB Site

23rd February 2025

Ticket#169411 | February 23, 2025| All Sites | Partial Disruption on Datacenter Internet Uplink

• Event : Partial Disruption on Internet Uplink

• Incident : February 23, 2025 (Sunday) | 9:30 PM (PHT) - Restored and for stability monitoring

• Activity Details : The affected circuit has been restored and subject for stability monitoring. We are still awaiting from our service provider for the root cause.

• Service Impact :Partial impact on network and internet connectivity – Restored


• Event : Partial Disruption on Internet Uplink

• Incident : February 23, 2025 (Sunday) | 8:27 PM (PHT) - On-going

• Activity Details : We have observed that one of our internet uplink is currently down and already coordinated it with our service provider.

During the incident, a partial impact on network and internet connectivity is expected as we have another internet uplink connection available for redundancy.

Apologies for any inconvenience it might have cause.

• Service Impact :Partial impact on network and internet connectivity – AllSites

22nd February 2025

No incidents reported

21st February 2025

No incidents reported

20th February 2025

No incidents reported