#SR-263497 | July 26, 2025 | All PH Sites | Site to Datacenter Circuit Network Maintenance

• Event: Service Provider New Firewall Migration

• Schedule: July 26, 2025 (Saturday) | 12:00 AM – 06:00 AM (PHT)

• Activity Details:

Hi Team,

As part of the ongoing efforts to provide an enhanced security and protection to our network, one of our service providers will conduct a Next Generation Firewall Upgrade on July 26, 2025, from 12:00 AM – 06:00 AM (PHT).

During the maintenance window, we expect a minimal to no impact on internet and network connectivity as automatic failover mechanisms are in place to ensure service continuity.

Further updates shall be provided as soon as they are available.

• Service Impact: Minimal to No Impact on Internet and Network Connectivity - All PH Sites

#SR-262892 | July 26, 2025 | 6F PNB Building, Makati | Uninterruptible Power Supply Replacement

• Event: New Uninterruptible Power Supply (UPS) Installation

• Schedule: July 26, 2025 (Saturday) | 08:00 AM – 12:00 PM (PHT)

• Activity Details:

Hi Team,

Our systems engineering and administration team will be installing a New Uninterruptible Power Supply (UPS) to replace the old UPS to avoid and mitigate the risk of power issues on our networking devices.

During the maintenance window, brief interruptions may occur as we replace the UPS units one at a time to minimize interruption and to ensure network and internet availability. Please note that users connected via Wired/LAN may experience temporary disruptions.

As a temporary alternative, we recommend connecting to #EmaptaExperience Wireless SSID to maintain internet access during the said activity.

For any additional support, please reach out to our Onsite Service Desk.

• Service Impact: July 26, 2025 (Saturday) | 08:00 AM – 12:00 PM (PHT)

Past Incidents

14th April 2023

Ticket#10211454 | April 14, 2023 | All Sites | ENET SSID Decommissioning, scheduled 2 years ago

• Event : Decommissioning of ENET SSID Across All Sites

• Schedule : April 14, 2023 (Friday) |

• Activity Details : In our continuing efforts to improve the wireless experience across all sites, We are encouraging all EMAPTA Core Employees to start utilizing the new #EmaptaExperience wireless SSID starting today until the 7th of April. We will be decommissioning "ENET" wireless SSID on the 14th or April.

Our client-facing wireless SSID "E" will be unaffected by this change and will have another set of transition schedule and notification to be put in place.

• Service Impact : No connection to ENET SSID will be available after April 14, 2023.

• Status: Completed

8th April 2023

Ticket#10210262| April 08, 2023 |OSB| Electrical System Preventive Maintenance, scheduled 2 years ago

• Event : Power Service Maintenance

• Schedule : April 08, 2023 (Saturday) | 7:00 AM – Onwards (PHT)

• Activity Details : Our facilities and building admin will be conducting an annual electrical system preventive maintenance to guarantee continuous excellent performance of our building’s electrical system. During the maintenance window, there will be a total outage on the power supply of the building for a minimum of eight (8) hours since they will be shutting down the main power and generators sets will not be operational.

• Service Impact : Total Outage of Power Supply

• Status: Completed

7th April 2023

Ticket#10210265 | April 07 - 08, 2023| SFS | Annual Preventive Maintenance, scheduled 2 years ago

• Event : Power Service Maintenance

• Schedule : April 07, 2023 (Friday) 11:00 PM to April 08, 2023 (Saturday) 8:00 AM (PHT)

• Activity Details : Our facilities and building admin will be conducting an annual preventive maintenance which includes transformers, switch gears and other electrical accessories to be inspected and recalibrated if necessary. During the maintenance window, there will be a total outage on the power supply of the buildings since they will be shutting down the main power and generators sets will not be operational.

• Service Impact : Total Outage of Power Supply

• Status: Completed

5th April 2023

10210274 | 4/5/2023| BET | Annual Building Power shutdown at BDO Equitable Tower (BET), scheduled 2 years ago

• Event : Annual Building Power Shutdown

• Schedule : April 5, 2023 (Wednesday) at 8:00PM to April 9, 2023 (Sunday), 3:00PM (PH Time)

• Activity Details : Hi Team,

Our Facilities and Building Admin will be conducting a scheduled annual building power shutdown from April 5, 2023, to April 9, 2023, at our office in BDO Equitable Tower (BET).

Our office will experience a total loss of power during the maintenance period, as the generator sets will not be operational. In line with this, the network devices on-site will be powered down before the activity begins.

• Service Impact : Building Power Supply

• Status: Completed

1st April 2023

Ticket#10211764 | March 25, 2023 and April 1, 2023 | All Core Users | Microsoft Authenticator Number Matching, scheduled 2 years ago

• Event : Planned IT Infrastructure Maintenance - Scheduled

• Schedule : March 25, 2023 and April 1, 2023

• Activity Details : This is to inform you that our IT infrastructure team will be enabling the number matching for our M365 multifactor authentication to enhance the security feature, to prevent accidental approvals and to defend against MFA attacks.

Note: No user intervention is required.

The conditions below show the Multi Authenticator MFA experience.

  1. Require users to enter the number displayed on the sign-in screen when approving an MFA request in authenticator.
  2. Application context: Show users which application they’re signing into.
  3. Location context: Show users their sign-in location based on the IP address of the device they’re signing into.

Service Impact: All core staffs will need to comply.

28th March 2023

No incidents reported

27th March 2023

Ticket#10212126 | March 27, 2023 | NTB|IPLC Connectivity Outage

• Event : Unplanned IPLC Connectivity Outage

• Schedule : March 27, 2023 (Monday) | 6:03 am – 10:35 am (PHT) - Restored

• Activity Details : NCP IPLC has been successfully restored and monitored as up at exactly 10:35 am and stable for about 4 hours now. As observed also, NCP VPC were now at normal range latency.

• Service Impact : NCP IPLC Connectivity - Restored


• Event : Unplanned IPLC Connectivity Outage

• Schedule : March 27, 2023 (Monday) | 6:03 am – Ongoing (PHT)

• Activity Details : We have monitored that our NCP IPLC is currently down and we already coordinating this to our internet service provider and waiting for their response. During this incident time, the traffic will be automatically failover to the VPN connection resulting in increase of latency with the NCP VPCs.

• Service Impact : NCP IPLC Connectivity

26th March 2023

Ticket#10212074 | March 26, 2023| Baguio | Unscheduled Power Outage – Baguio Site

• Event : Unscheduled Power Outage – Baguio Site

• Event Start : March 26, 2023 (Sunday) | 6:07 PM – March 27, 2023 (Monday) | 1:34 PM (PHT)

• Status: Our NTB site has been back to normal operations and our network devices has been powered up and stable for two (2) days now. Also, we have been informed that the fire incident is due to an electrical surge/arcing on the building’s battery room as per Bureau of Fire Protection Baguio (BFP) investigation.

• Service Impact : NTB site operations - Back to Normal Operations


• Event : Unscheduled Power Outage – Baguio Site

• Event Start : 6:07PM

• Status: We have confirmed reports of a fire incident at our EMAPTA office in Baguio. We have also confirmed that the fire is out and are currently assessing the situation.

• Service Impact : NTB site operations

Ticket#10211503 | March 26, 2023 | PNB | Infrastructure Risk Analysis and Mitigation Plan, scheduled 2 years ago

• Event : Infrastructure Risk Analysis and Mitigation Plan

• Schedule : March 26, 2023 (Sunday) | 7:00 PM – 9:00 PM (PHT)

• Activity Details : As part of our on-going effort to provide service reliability, we filed a change request to conduct BCP failover testing on our PNB site. During the maintenance period, the entire site will have an intermittent LAN and wireless connectivity.

Our IT Infrastructure team will also be conducting necessary configuration changes and operating system updates on our networking devices during the provided time frame.

• Service Impact : Intermittent LAN and Wireless Connectivity

• Status: Incomplete, will request another schedule to continue the remaining floors.

Ticket#10206383 | March 26, 2023| SFS | Data Center Uplink Maintenance, scheduled 2 years ago

• Event : ISP Fiber Optic Cable Cut Over

• Primary Schedule : March 19, 2023 (Sunday) | 12:00 AM to 6:00 AM (PHT) - Cancelled • Secondary Schedule : March 26, 2023 (Sunday) | 12:00 AM to 6:00 AM (PHT) - Completed

• Activity Details :Our ISP informed us that the maintenance activity will be deferred on the primary schedule provided due to operational issues. With this, they will proceed on the backup schedule.

• Service Impact : Minimal to No Impact on SFS Internet Connectivity

• Status: Completed

25th March 2023

Ticket#10211617 | March 25, 2023 | TIM Data Center | Monthly Load Testing of Generator Sets, scheduled 2 years ago

• Event : TIM Data Center Monthly Load Testing of Generator Sets

• Schedule: March 25, 2023 - 8:40 AM - 5:25 PM (PHT) - Completed

• Activity Details : We received a confirmation that this activity has been successfully completed. No issues experience as expected.

• Service Impact : None

• Status: Completed


• Event : TIM Data Center Monthly Load Testing of Generator Sets

• Schedule: March 25, 2023 - 8:40 AM - 5:25 PM (PHT)

• Activity Details : Monthly Load Testing of Generator Sets

• Service Impact : None

• Status: Scheduled

24th March 2023

No incidents reported

23rd March 2023

Network and Internet Ticket#10211627 | March 23, 2022| NTB| Partial Network Outage at Netrinos Building Pilando Center (NTB)

• Event : Unplanned Internet Service Provider Network Outage.

• Schedule : March 23, 2022 (Thursday) |11:04 PM (PHT) - Ongoing

• Details : One of our circuit uplinks is currently monitored as down. We are already coordinating this to our internet service provider and waiting for their response. Just a partial to NO impact should be expected as we have another circuit uplink available to our internet gateway.

• Service Impact : Partial to NO Impact on Network and Internet Connectivity

• Issue: Fibre breakage in the area. Resolved 11:47 AM.

22nd March 2023

Ticket#10211221| March 22, 2023| PNB | Emergency Network Maintenance, scheduled 2 years ago

• Event: Emergency Network Maintenance

• Schedule: March 22, 2022 (Wednesday) | 8:00 PM - 9:00 PM

• Activity Details: Replacement of distribution switch

• Service Impact: Network and Internet Connectivity

• Status: Completed

Ticket#10211175 | March 22, 2023| PNB | Network Interruption, scheduled 2 years ago

• Event: Network Incident

• Schedule: March 22, 2022 (Wednesday) | 2:46 PM - Ongoing (PH Time)

• Activity Details: A network incident has been observed affecting certain floors of our PNB site in Makati. The issues are affecting PNB lower ground floor, 6th, 10th, and 11th floors. We are currently investigating the cause of this and will revert with updates once we have the findings. EMAPTA IT Infrastructure team is on-site and conducting the necessary troubleshooting to resolve the issue.

• Service Impact: Network and Internet Connectivity

21st March 2023

Ticket# 10210386 | March 21, 2023 | IPLC | IPLC Connectivity Maintenance, scheduled 2 years ago

• Event : Planned IPLC Connectivity Maintenance

• Schedule : March 21, 2022 (Tuesday) at 5:00 AM to 1:00 PM (PH Time)

• Activity Details : Emergency maintenance will be performed in order to fix a damaged cable in the Paris area.

• Service Impact : No outage expected

• Status: Completed

20th March 2023

No incidents reported

19th March 2023

No incidents reported